USE Case Point Estimation

Posted by: Mohamed Elashri on: June 30, 2008

Use Case Estimation
Use Case Points (UCP) is an estimation method that provides the ability to estimate an application’s size and effort from its use cases.
UCP analyzes the use case actors, scenarios and various technical and environmental factors and abstracts them into an equation.
The equation is composed of four variables:

Technical Complexity Factor (TCF).
Environment Complexity Factor (ECF).
Unadjusted [...]